| Planning note: The figures below are broad U.S. budgeting estimates, not a quote. Costs vary with location, home size, design, site conditions, access, labor rates, and local requirements. The examples assume a roughly 1,500-square-foot home and exclude land unless noted. |
| Factory-built home package | Approximately $120,000–$240,000 | May include the modules, standard finishes, and specified fixtures. Package inclusions differ substantially between proposals. | Request an itemized inclusions-and-exclusions list. Check whether appliances, stairs, porches, exterior finishes, and delivery are included. |
| Foundation and site preparation | Approximately $20,000–$60,000 | May cover clearing, grading, excavation, drainage, and a foundation. Sloped, rocky, or wet sites can increase costs. | Confirm who pays for soil testing, engineering, retaining walls, and unexpected subsurface conditions. Ask how changes are priced and approved. |
| Transport and crane setting | Approximately $8,000–$30,000 combined | Transport depends on distance, route, permits, escorts, and access. Crane costs depend on equipment, setup, and site conditions. | Identify the delivery point and responsibility for route surveys, road permits, escorts, crane access, and costs if delivery is delayed. |
| Utility connections | Approximately $5,000–$30,000 or more | Water, sewer or septic, electricity, gas, and communications connections. Long runs or off-grid systems may cost more. | Confirm which connections are included, who obtains approvals, and whether utility-provider fees and trenching are part of the estimate. |
| Permits, engineering, and inspections | Approximately $3,000–$15,000; timing often 1–4 months or longer | Local building permits, site-specific engineering, plan reviews, and required inspections. Approval times depend on the jurisdiction. | Confirm who submits plans and pays fees. Check that the design meets local codes and that the schedule accounts for review and resubmission time. |
| Finishing and completion work | Approximately $15,000–$50,000 | May include module connections, finish carpentry, steps, porches, driveways, landscaping, and other work needed for move-in. | Define the completion standard, punch-list process, cleanup, warranty coverage, and the party responsible for each trade. |
| Estimated project total, excluding land | Approximately $170,000–$425,000 | A broad planning range for the home package and common site, delivery, utility, permit, and completion costs. It is not a guaranteed installed price. | Compare written, scope-matched estimates. Keep a contingency for site-specific work and ask which costs are fixed, allowances, or subject to change. |
| Contract price and payment schedule | Milestone-based payments are common; exact terms vary | Contracts may separate design, factory production, delivery, setting, and final completion payments. | Check deposit terms, payment triggers, change-order approvals, cancellation rights, refund terms, delay remedies, and whether funds are protected. |
| Design and engineering | Approximately 2–8 weeks | Plan selection or customization, structural details, site adaptation, and preparation of permit documents. | Confirm when the design is considered final, how many revisions are included, and whether later changes affect price or production dates. |
| Factory production | Approximately 8–16 weeks after final approvals and production release | Manufacturing of modules and factory inspections. Start dates generally depend on completed plans, approvals, and required payments. | Ask what conditions start the production clock, how schedule updates are provided, and how material shortages or production delays are handled. |
| Site work and foundation | Approximately 2–8 weeks; may overlap with factory production | Site preparation, foundation construction, and utility work where conditions and permits allow. | Agree on readiness requirements for delivery, weather contingencies, responsibility for site access, and costs if the site is not ready. |
| Delivery and module setting | Transport and crane setting commonly take 1–3 days once the site is ready | Modules are transported to the property and placed on the prepared foundation. Final timing depends on route, weather, and crane access. | Confirm delivery windows, access dimensions, temporary road requirements, weather postponement terms, and who coordinates the crane and transport. |
| On-site completion and move-in readiness | Approximately 4–12 weeks after setting, depending on scope | Module connections, finishing, utility commissioning, inspections, and correction of outstanding items. | Request a written completion schedule and define final acceptance, occupancy approvals, warranty start date, and how unresolved punch-list items are handled. |